ml_player_7_small.jpgConstruction for ALLPLAY Complex will begin on April  21, 2008.  Construction of the complex is scheduled in two seperate phases:

Phase I: April 21 through July 10, 2008. This phase of construction will include: general site preparations (grading, drainage, terracing),  the "Miracle League" baseball field, wheelchair softball field, and parking lot. 

Phase II: Based on fundraising efforts (tentative 2009)  This phase will include:  playground, zero enrty water park, family pavilion, batting cate, storage shed, restroom remodeling, scoreboards, and other features.

The William and Ruth Scott Foundation, Peter Kiewit Foundation, and proceeds from the sale of an assessible home on the 2007 Street of Dreams built by Curt Hofer and Alegent have generoulsy contributed to allow  the building of phase I.  Donors are being sought to allow phase II construction to be scheduled.